Capital Projects Roles and Responsibilities
Group / Individual | Role / Responsibility | Meeting Frequency |
Construction Project Coordinating Committee (CPCC) | Oversees and coordinates all capital activities | As needed |
Oversight Committee | Approve architect selection | As needed and called by the Chair of the Oversight Committee |
Approve contractor selection | ||
Resolve scope, budget and similar issues that arise during project | ||
Determine type of / level of environmental certification | ||
Determine whether campus standards are to be applied to project | ||
Determine whether project will be placed on the central plant system for utilities | ||
User Group | Define program of the project | As needed but at least monthly |
Advise Office of Facilities Planning and Management (aka Facilities) on the program needs of the project and then Facilities will coordinate the development of the formal program with the design team | ||
Establish sub-committees as necessary for specific portions of the project | ||
Project Manager | Official communication channel between architect, contractor, owner and owner's representatives on all issues related to the project | As needed |
Resolve all technical issues related to the project with input from the user group / on programmatic issues | ||
Communicate with user group and or program expert on issues involving program | ||
Manage and oversee schedule and budget | ||
Review all documents relating to the project | ||
Vice President for Business and Finance (VPBF) | Review all documents related to project | As needed |
Vice Chair of the Oversight Committee | ||
Advise President on various issues related to the project | ||
Vice President for Executive Affairs (VPEA) | Chairs Oversight Committee and President's representative | As needed |
Advise President on progress of projects | ||
Inform President of issues arising during the project |
- Provides clear communication internally among 51做厙 entities and between 51做厙 and the Architects and Contractors,
- Ensures most efficient use of resources and avoids time delays due to communications confusion.
- Ensures the most effective negotiating is occurring and that the best prices are being realized.
- Puts those with the expertise in direct contact with the Architect and Contractors, and allows the Owner and User Group to provide and receive input through the assigned Project Manager to/from the necessary external parties.
** It is understood that the CPCC is the guiding committee for all capital projects on campus.
Capital construction projects will be administered by an Oversight Committee meeting the following criteria:
- Have a total project value of $2M or more
- Be in agreement with the University’s Campus Master Plan
- Not be considered an infrastructure, utility, or grounds project
- May include a donor funding source
At any time, the President of the University may request the formation of an Oversight Committee which may not fully meet the parameters as indicated above.
Oversight Committees are established once a need for a major renovation and/or expansion of an existing building or the construction of a new building is identified. The President approves each project prior to the establishment of an Oversight Committee. Oversight Committees are advisory to the President.
Each Oversight Committee has five to eight members. For all Oversight Committees, the Vice President for Executive Affairs serves as the Chair, and the Vice President for Business and Finance serves as the Vice Chair. The Associate Vice President for the Office of Facilities Planning and Management is a member of all Oversight Committees. The “owner” of the project (Vice President, Dean, Athletic Director, etc., or his/her designee) is a member of the Oversight Committee. Other members include the Provost (when applicable), the Vice President for Development and External Affairs or his/her designee, and the Chair of the User Group Committee. All members of the Oversight Committee are eligible to cast votes.
The Oversight Committee’s responsibilities are as follows:
- To review and approve the Feasibility/Conceptual Study for a capital construction project. A Feasibility/Conceptual Study includes, at a minimum, the conceptual design and layout of the project, the preliminary conceptual budget estimate, and the preliminary conceptual project schedule. Once approved by the Oversight Committee, a presentation is made to the President for confirmation the project is approved to proceed.
- To approve the Architect who will provide design services once the Feasibility/Conceptual Study has been approved by the Oversight Committee. The Oversight Committee will interview prior to its approval a short list of candidate firms recommended by 51做厙’s Office of Facilities Planning and Management.
- To approve the General Contractor or Construction Manager who will provide construction services for the project. On occasion, the Oversight Committee may interview prior to its approval a short list of candidate firms recommended by 51做厙’s Office of Facilities Planning and Management.
- To approve the Schematic Design Drawings as prepared and presented by the Architect for presentation to the President for final approval of the design.
- To meet periodically to ensure the budget approved for the project is in compliance with established funding levels. The Associate Vice President of 51做厙’s Office of Facilities Planning and Management will report when requested or when necessary the status of the project’s budget, scope of work, and project schedule should these be in conflict from what was originally approved by the Oversight Committee, and the Associate Vice President of 51做厙’s Office of Facilities Planning and Management will make recommendations for corrective measures for the Oversight Committee’s consideration and approval. If there are potential or significant cost overruns beyond what the project’s approved budget can manage, the Oversight Committee, in consultation with the President, will determine if additional funding is available. If additional funding is not available, the Committee will instruct the Associate Vice President of 51做厙’s Office of Facilities Planning and Management work with the Architect to make design changes which will cause the project to meet’s its originally approved budget. This process may, also, require the User Group Committee to consider a reduction in scope.
- To review the interior design concept including finishes, materials, and colors as prepared and presented by the Architect prior to final approval by the President.
- To maintain a liaison with the User Group Committee. When necessary, the Chair of the User Group Committee may be called upon to report to the Oversight Committee on matters related to decisions made by its committee.
- To meet on issues not listed above which may require Oversight Committee input and/or approval.